M&E and Telecoms services for Morgan Sindall Infrastructure
Initiative
The Northumberland Line is designed to stimulate economic growth, regeneration, and community development across Northumberland and the surrounding regions. The project will deliver new and improved transport links for local people and businesses, leaving a positive and lasting legacy.
Bedlington Station, the last of six new stations constructed as part of the project, opened on 29 March 2026.
Implementation
Forte Engineering delivered the mechanical, electrical and telecoms installation for the two platform station and car park including:
Expertise
The Bedlington Station programme was challenging due to the presence of many unmapped buried utilities (many associated with the railway line) and constraints due to working next to an operating railway line.
Our flexible approach ensured we could adapt to installing elements, for example, platform lighting, as soon as conditions allowed.
Works were further impacted by the presence of level crossings near the station, requiring careful planning to ensure deliveries to site were not scheduled when the crossing was closed.
The final station to open on the Northumberland Line, Bedlington will:
Social Value
Embedding sustainable and social value principles is integral to our approach. We achieved the following on this project: